Jacking System Verification Services for ADNOC (UAE)

Client: ADNOC
Provided services: Jacking System Verification
Duration: 2023-2026
Location: UAE

In 2023 ALMAEER was awarded with a 3-year contract with ADNOC.  We provide Jacking System Verification Services for the 77 ADNOC Offshore Jack-up Rigs & Barges.

Jacking Systems are identified by ADNOC as a critical equipment system on offshore jack-up units. To minimize the risks of failure of the physical assets, ADNOC has directed ALMAEER to carry out independent verification of the jacking systems on all ADNOC contracted jack up rigs and jack up barges.

Jacking System Assurance Audits covering:

  • Jacking equipment audit review to OEM and relevant standards indicating gaps where applicable.
  • Monitoring of jacking trials, reviewing the functionality of the complete system operationally.
  • Acceptance of all components and functionality with written documentation.
  • Review recorded preventative maintenance history(s), in-house inspection reports by rig personnel, and 3rd party survey documentation for the jacking system related equipment and main generators, and indicate gaps where applicable.
  • Review operational certification.
  • Jacking control system audit to OEM and relevant standards.
  • Where required, physically review wear on major components and carry out comparison checks with permissible tolerances using calibrated/certified Vernier and depth gauges.
  • Review jacking system life rating calculations and detailed inspection intervals.
  • Review competency levels.
  • Spud can strength assessment.

Rig condition survey and CAT IV Inspection for ERIELL (Uzbekistan)

Client: EREIELL GROUP
Provided services: Rig inspection services
Duration: 2024
Location: Uzbekistan

Almaeer has been awarded with a contract to provide Rig inspection services for ERIELL GROUP on their land rig ZJ-70 based in Uzbekistan.

This Project composes of two phases:  Phase 1 being the Rig Condition Survey, and Phase 2 the CAT IV Inspection (including NDT Inspection).

Audit Objectives for this project shall encompass the following:

  • Assess equipment availability and readiness as per Client Audit Procedure for Drilling, Workover and Well Service Units.
  • Assess the technical condition of the rig and associated equipment for upcoming project(s).
  • Fully recertify the drilling unit and associated components to all recognized local and international standards, covering API STD 53 / API RP 4G/8B/7L CAT inspections.
  • Safety and Environmental Critical Elements Management.
  • Review the Contractor Management System with respect to rigs and associated equipment and assess their implementation.
  • Assess the contractor`s personnel level of training and competence.
  • Assess sub-contractor’s management.

Acceptance audit of the mast raising equipment  (UAE)

Client: Ocean Oil Services ( HILONG HOLDING LIMITED) 
Provided services:  Acceptance audit of the mast raising equipment
Duration:  2023-2023
Location:  Sharjah, UAE

OCEAN OIL SERVICES (a wholly owned subsidiary of ”HILONG HOLDING LIMITED”) requested Almaeer to perform an acceptance audit of the mast raising equipment on their rig HL30, located in Sharjah field.

The scope of work included the following::

  • Visit the rig site and conduct inspections, testing and examinations of Safety Critical Elements (SCE’s) to ensure their continued suitability.
  • Carry out/witness examination and testing of SCE’s including all documentation/certification and CE marking pertaining to same.
  • Auditing the maintenance regime currently in place, to ensure the equipment is maintained to the required regulatory standards, and is still viable for the requirements.
  • Reviewing associated data in association with HSE regarding Mast Raising.

Pre-hire audit for land rig (Poland)

Client: U.DRILL LLC
Provided services:  Pre-hire audit
Duration:  2023-2023
Location:  Poland

U.DRILL LLC has requested ALMAEER to carry out a rig pre-hire audit on one of their clients’ land rigs BK-68 in Eastern Europe.

Inspection was conducted according the following audit objectives:

  • Assess equipment availability and readiness as per client Audit Procedure for Drilling, Workover and Well Service Units.
  • Safety and Environmental Critical Elements Management.
  • Assess the technical condition of the rig and associated equipment for the upcoming project.
  • To review the contractor`s management system with respect to rigs and associated equipment and assess their implementation.
  • To assess the contractor`s personnel training and competence.
  • To assess sub-contractor’s management capabilities of the project.

Shipyard refurbishment project evaluation audit (Bahrain)

Client: Dynamic Drilling and Services 
Provided services:  Provide shipyard refurbishment project evaluation audit
Duration:  2023-2023
Location:  Bahrain

Dynamic Drilling and Services PLC has requested ALMAEER to provide Shipyard refurbishment project evaluation audit for their rig Divine Driller (Marathon Le Tourneau Class 116-C) in the ASRY shipyard in Bahrain.

The rig inspection audit included the following requirements:

  • To assess work done to date according to compliance. We are carrying out a 3rd party independent verification audit of ongoing shipyard refurbishment work including the new drilling derrick installation and electrical components reinstalled during shipyard campaign.
  • To review and independently advise on forward planning of work to compliance and OEM standards.
  • MODU code upgrade from 1979 to 1989 to review (Gap analysis)

Pre-hire and Commissioning Survey for Almansoori / Taq Taq Operating Company (Iraq)

Client: Almansoori/Taq Taq Operating Company
Provided services:  Rig pre-hire audit and electrical camp inspection for the land rig
Duration:  2023-2023
Location:  Iraq

ALMAEER has been conducted pre-hire audit and electrical camp inspection for the land rig HONESTAR HS-036.

The scope of work included the following:

  • Assess equipment availability and readiness as per client Audit Procedure for Drilling, Workover and Well Service Units.
  • Safety and Environmental Critical Elements Management.
  • Assess the technical condition of the rig and associated equipment for the upcoming project.
  • Electrical camp inspection primarily Power Generation, Power Transmission, Main Distribution and Sub Distribution Panel, Laundry Cabin, Residents Cabin. 
  • To review the contractor`s management system with respect to rigs and associated equipment and assess their implementation.
  • To assess the contractor`s personnel training and competence.
  • To assess the sub-contractor’s management.

Acceptance Mechanical Audit on the Rig for Selective Marine Services (UAE)

Client:  Selective Marin Services
Provided services:  Specific Acceptance Mechanical audit covering ANDOC compliance standards
Duration:  2020-2020
Location:  China

ALMAEER carried out specific ADNOC acceptance audit for SMS ESSA Le Tourneau S 116E at COSCO shipyard Dalian China to facilitate smooth acceptance by ADNOC covering all ADNOC compliance standards.

The survey included the following Mechanical requirements:

  • Rig Surveys and Inspection to the recognized international standards including the ADNOC Jack Up Integrity Management Standard (JUIMS)
  • Mechanical Condition Survey.
  • Review outstanding Mechanical shipyard construction issues.
  • Review questionable equipment accreditation and highlight areas of concern.

 

Rig condition surveys for the National Oilwells Drilling & Workover Company (Libya)

Client: National Oilwells Drilling & Workover Company / ALMANSOORI
Provided services: 
SAPI RP 4G, 7L, 8B Cat III,
API RP 4G Cat IV
Duration:  2022-2022
Location:  Libya

In 2022 ALMAEER was chosen by National Oilwells Drilling & Workover Company for the follow services for their rigs and units in Libya:

  • API RP 4G, 7L, 8B Category III Survey of Mast and Substructure and Rig Components
  • API RP 4G Category IV Inspection, Survey of Mast and Substructure (Full disassembly of the substructure and mast components along will full MPI/NDT of all high stress areas along with welded connections).

Commissioning and rig condition surveys for the Damson Energy (UAE)

Client: Damson Energy / ALMANSOORI
Provided services: Rig API 8B/7L/4G CAT III Refurbishment Acceptance
Duration:  2021-2021
Location:  UAE

Damson Energy has directed ALMAEER to perform commissioning and rig condition surveys for their rigs and units located in UAE.

ALMAEER performed Reactivation Commissioning and API RP 4G, 7L, 8B work scopes to ADNOC acceptance requirements and Condition Survey to applicable standards API RP 4G, 7L, 8B work scopes to ADNOC acceptance requirements.

Full condition inspection for Urja Bharat Pte (UAE)

Client: Urja Bharat Pte / ALMANSOORI
Provided services: Full condition acceptance audit  
Duration:  2022-2022
Location:  UAE

ALMAEER carried out full condition acceptance for land rig AD 125 to prepare them for operations with ADNOC Onshore. All applicable ADNOC standards were utilized and audits done accordingly.   

Objectives for this audit were:

  • Assess equipment availability and readiness as per applicable standards within this report
  • Safety and Environmental Critical Elements Management.
  • Assess the technical condition of the rig and associated equipment for upcoming project(s).
  • To review contractor`s management system with respect to rigs and associated equipment and assess their implementation.